Home » Case Studies » Healthcare » Accident & Emergency Department

Duration

30 weeks

Value

£1.0 million

Scope of works

The project consisted of the reconfiguration of the existing Accident & Emergency Department at St James’s University Hospital Leeds. The works were undertaken in 3 separate phases whilst maintaining the operating functions of an existing Accident & Emergency Department which entailed that when access was required through the site by the client works had to cease until the client had left the site area.

The works incorporated:

  • Full strip out of the A&E Department
  • Full M&E services strip out and re-installation
  • Flooring, wall protections, internal doors, screens, suspended ceilings and full decoration package

The scheme also incorporated the full be-spoke joinery manufacuture of client specified nurse base stations.

Roles & Responsibilities

Principal Contractor 

Contract type

JCT Standard Building Contract without Quantities with Sectional Completion