Duration

28 weeks

Value

£1.4 million

Adsett & Collegiate Centre image 1Adsett & Collegiate Centre image 2Adsett & Collegiate Centre image 3

Scope of works

The works were undertake for Sheffield Hallam University over two seperate locations on the Sheffield Hallam Estate; incorporating a full design & build refurbishment package.

The design required a full internal strip out to all areas and then the full internal refurbishment and re-configuration of the Collegiate and Adsetts Centres. The works provided the client with a new state of the art library, teaching spaces, communal areas and learning facilities.

Roles & Responsibilities

Principal Contractor

Contract type

JCT Building Contract with Contractor Design